Location |
Phetchabun |
Start |
September 2019 |
Finish |
January 2020 |
Load |
Turn key THB 12.30 Million |
Load |
500 kVA |
Man-hours |
15,776 MH used for one farm 20 peoples at peak for one farm |
Safety incident |
LTls : ZERO MTls : ZERO |
Scope |
Design supply and installation of
|