Location |
Angthong |
|
Start |
February 2012 |
|
Finish |
May 2012 |
|
Contract |
Turn key THB 14.30 Million |
|
Load |
630 kVA |
|
Man-hours |
22,400 MH used 20 people at peak |
|
Safety incident |
LTls : ZERO MTls : ZERO |
|
Scope |
Design supply and installation of
|