Location |
Chonburi |
Start |
July 2008 |
Finish |
October 2008 |
Contract |
Lump sum THB 9.25 Million |
Load |
55000kVA |
Man-hours |
23,000 MH used 230 people at peak |
Safety incident |
LTls : ZERO MTls : ZERO |
Scope |
Design supply and installation of
|